what is the earliest date on which a claimant may seek a remedy when an anticipatory breach of contract occurs? A.the date on which notice of non-performance is given B.the date on which the contact is due to be performed C.the date on which the parties entered into the contact 我有點不明白為什么選c 我覺得預期違約是在一方覺得自己違約了然后告知另一方時,這時另一方可以起訴然后得到賠償

Yoo 發(fā)布于:2020-07-31 04:38:53 瀏覽263次   ACCA LW
添加圖片
0/1000

名師解答

JasmineLiu 發(fā)布于2020-07-31 13:03:14

加載中...